KCCI submits memorandum to DK DC on closure of Shiradi Ghat road closure for 6 mths
Team Udayavani, Jan 13, 2022, 5:48 PM IST
The Kanara Chamber of Commerce & Industry (KCCI) has submitted a memorandum to Dakshina Kannada Deputy Commissioner on the closure of NH 75 from Donigal and Maranahalli for the construction of four-lane works. As per media reports, the work on the project is likely to be completed in six months.
In the letter, KCCI President Shashidhar Pai Maroor expressed that if meticulously planned the work can be executed in a much lesser period to avoid inconvenience to the general public and economic activities of Dakshina Kannada district.
The contents of the letter are as below:
It has come to our knowledge from the media report about the closure of NH 75 from Donigal and Maranahalli for the construction of four lane works. Report also mentions a meeting being held between NHAI officials and the contractors to discuss this 10-kilometer road project. The project is expected to complete in six months, says the news report and with the complete closure of roads during this period.
NH 75 is the main connection to the capital city of Bengaluru. Closure of this route will cause huge inconvenience to citizens of all sections and majorly hinder trade, commerce and industrial activities of this region.
People of coastal districts have already experienced hardships in the past when this stretch of NH 75 was closed multiple times for repair and laying of roads for long unreasonable periods.
The closure of NH 75 will affect the entire trade as currently the alternative routes to these areas are closed due to restriction imposed by the Kodagu district on Sampaje ghat as well as restrictions in the movement of multi axle vehicles on Charmadi Ghat. Shiradi Ghat plays an important role in movement of export and import cargo from Hassan, Kushalnagar and Chikmagalur to the port city.
While we appreciate this progressive project, the six months’ time to repair the stretch of 10 Kms is too much time taken. We are of the view that with proper planning, this work can be executed in a much lesser period to avoid inconvenience to general public and economic activities of Dakshina Kannada district.
It will be devastating if trade activities are affected as already many have suffered heavily in the past lockdown. We request you to:-
1. Permit cargo movements on the above routes whilst the repairs are being carried out in order to support the trade.
2. Prioritize and ensure expediting the work to a timeframe of less than 3-4 months and permit light vehicular traffic at the earliest in this period.
3. To constitute an independent committee by the district administration to assess the methodology and time requirement of this project completion.
4. Make concerned NHAI officials and the contractor accountable for any lapse.
Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.
Top News
Related Articles More
Mangaluru: Car catches fire near Kadri Police Station
Bengaluru: Family donates organs of 37-year-old man
Kumaraswamy demands SIT probe into allegation of Rs 50 cr for 50 Cong MLAs
Udupi: Free registration on NFDP portal for fishermen under PM-MKSSY
Karkala: Depressed after husband’s death, Anganwadi teacher dies by suicide
MUST WATCH
Latest Additions
1951 Rolls Royce ordered by Nehru for Baroda ‘maharani’ becomes flashpoint in marital dispute
Mangaluru: Car catches fire near Kadri Police Station
Misuse of social media platforms by terrorists to be borne in mind by courts while sentencing: HC
Bengaluru: Family donates organs of 37-year-old man
J-K: 2 teenage boys driving SUV die in road accident; sparks calls to curb underage driving
Thanks for visiting Udayavani
You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.