NGT quashes EC to luxury project in Bengaluru, orders immediate demolition
PTI, Jul 30, 2021, 6:06 PM IST
The National Green Tribunal Friday quashed the environmental clearance (EC) granted to a high-rise luxury project by Godrej Properties Limited and Wonder Projects Development Private Limited in Bengaluru and directed its immediate demolition.
The green panel also imposed a penalty of Rs 31 crores on the project proponent and said the amount shall be used for demolition of the constructions, restoration of the area to the original position, rejuvenation and reforestation of the ―Kaikondarahalli lake and its surrounding area.
A bench headed by by NGT Chairperson Justice Adarsh Kumar Goel also imposed a cost of Rs 10 lakh on Bruhat Bengaluru Mahanagara Palike (BBMP)which allowed construction/alteration of Storm Water Drain passing through the project site illegally.
“EC dated January 10, 2018 is quashed,” the bench said.
The order came on a petition filed by Bengaluru resident H P Rajanna against the project, Godrej Reflections, being built at Kasavanahalli village in Varthur Hobli in Battleground Urban district.
Noting that the construction raised by project proponent commenced even before grant of Consent to Establish by Karnataka State Pollution Control Board (KSPCB) and in violation of conditions of EC, the NGT directed that the constructions made on site shall be demolished immediately.
“We impose compensation for damage to environment as 10 per cent of the cost of project.
The cost of project mentioned in the application submitted for grant of EC was Rs 310 crores, hence project proponent is directed to pay Rs 31 crores.
“This amount shall be used for demolition of the constructions as per direction (ii), restoration of the area to the original position, rejuvenation and reforestation etc.
of the ―Kaikondarahalli lake and its surrounding area,” the bench said.
The tribunal said the penalty shall be utilised by preparing a restoration plan by the said authority with the assistance of the BBMP, KSPCB and Central Pollution Control Board (CPCB).
Restoration plan shall be executed by State Wetland Authority and BBMP which may also be overseen by KSPCB and CPCB, it said.
The restoration plan be prepared within two months and executed within one year, the NGT said while making it clear that if any amount remains available after undertaking the restoration work, the same will be utilised by the Wetland Authority for maintenance and beautification of the lakes in question.
“If the amount is found to be deficient, the deficiency will be made up by BBMP.
If any question remains unresolved, but in the authorities, the National Wetland Authority is directed to resolve the same,” the bench said.
The tribunal said the confidence of the project proponent in proceeding ahead at different levels without caring for Statuary Provisions, Procedures and Environmental Laws, supported by some of the statutory authorities is evident by the conduct of senior officers of various departments who were appointed members of the Committee by Tribunal and Environment Ministry, yet they defied the same.
“It appears that in a concerted way, some officials have acted to somehow justify patent illegality and bold defiance of law on the part of project proponent.
“ Clearly, there is an evident lack of bonafide on the part of the officials and this conduct deserves to be strongly condemned.
We will request Secretary, MoEF (Ministry of Environment and Forest) to look into the matter and take appropriate action against such erring officials,” the bench said.
Rajanna challenged a State Environment Impact Assessment Authority order dated January 10, 2018, granting an EC to the project at survey nos.
61/2, 62 and 63/2, Kasavanahalli village, Varthur Hobli, Bengaluru East Taluk and Bengaluru district.
Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.
Top News
Related Articles More
Congress’ guarantees implemented in Karnataka amid BJP’s false propaganda: Shivakumar
Only ineligible BPL cards will be weeded out, no impact on eligible cardholders: K’taka CM
‘Kantara: Chapter 1’ to release on October 2, 2025
Lokayukta report has cleared previous BJP govt from 40% commission charges, claim party leaders
Ullal: Three students drown in resort swimming pool
MUST WATCH
Latest Additions
Congress’ guarantees implemented in Karnataka amid BJP’s false propaganda: Shivakumar
Followers of Sanatan Dharma will respond to those disrespecting it: Pawan Kalyan
Pushpa bows down to no one, but will do so for you: Allu Arjun to fans at ‘Pushpa 2’ trailer launch
Priyanka Gandhi leads roadshow in Nagpur
Sport teaches values beyond competition: Srihari Nataraj
Thanks for visiting Udayavani
You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.