NHPC to commission 2,000 MW hydropower project on Subansiri by March 2022


PTI, Dec 6, 2020, 8:33 AM IST

Guwahati: PSU major NHPC Ltd on Saturday said the 2,000 MW Subansiri hydropower project, which was stalled for nearly eight years due to intense protests by many groups in Assam, will be commissioned by March 2022.

Union power ministry”s secretary Sanjiv Nandan Sahai, Arunachal Pradesh chief secretary Naresh Kumar and the company”s chairman and managing director A K Singh visited the Subansiri Lower Hydro Electric project sites on Friday and inaugurated the restart of the power-house works, NHPC said in a statement.

“Later in the day, the power secretary held a review meeting wherein NHPC chief briefed about the various construction activities and downstream river protection works undertaken by the company. It was assured that the project shall be commissioned by March 2022,” it added.

Construction work of the ambitious project at Gerukamukh along the Assam-Arunachal Pradesh border on Subansiri river was halted from December 2011 to October 2019 due to protests by locals and many groups fearing about safety and the adverse impact on the downstream of the river.

According to a company estimate in January 2020, the cost of the mega project, which was scheduled to be commissioned in December 2012, had escalated to around Rs 20,000 crore.

The initial project cost was estimated at Rs 6,285 crore.

The Centre had allocated a total of Rs 11,000 crore as of December 2010 for construction of the dam.

Multiple committees were formed by the Assam government and the Centre to address the concern of the agitators. The outcomes of their reports varied from one to another.

Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.

Top News

Nadda’s letter to Kharge full of falsehoods: Cong

10 month baby gets new heart, new life

Actress Kasthuri released from jail, says ‘I thank those who made me raging storm’

Kidnapped for ransom in 1998, 26/11 survivor Gautam Adani faces biggest trial

100 engineering colleges in Karnataka to be ‘adopted’ by corporates by next year: IT Minister Kharge

Siddaramaiah defends BPL ration card cancellation, says only ineligible beneficiaries affected

China announces new policy measures to protect its exports from Trump’s new tariff threat

Related Articles More

Kidnapped for ransom in 1998, 26/11 survivor Gautam Adani faces biggest trial

Gautam Adani charged in US with USD 250 mn bribery, fraud

India’s GDP growth likely to slip at 6.5 pc, maintains 7 pc estimate for FY25: Icra

RBI cautions public about ‘deepfake’ video of governor being circulated on social media

We disagree with decision, plan to appeal: Meta on CCI imposing Rs 213-cr penalty

MUST WATCH

Christmas Cake Fruit Mixing

DK Shivakumar

Rose Cultivation

Geethotsava

Naxal Operation


Latest Additions

Sampaje: Financial fraud using Google Pay reported

Nadda’s letter to Kharge full of falsehoods: Cong

Kundapur: Several injured after insulator truck rams into Innova car on NH-66

Only ineligible BPL cards cancelled: Dinesh Gundu Rao

Fraudsters create fake FB profile misusing Udupi DC’s identity, case filed

Thanks for visiting Udayavani

You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.