Second six-car train to be operational by Sept end
Team Udayavani, Sep 8, 2018, 10:44 AM IST
Bengaluru: Bangalore Metro Rail Corporation Limited (BMRCL) officials said that Namma Metro’s second six-car train will be operational by the end of September.
The officials said that train was received at Byappanahalli depot on Thursday evening and it may take about three weeks to assemble the coaches.
The BMRCL on Friday started working on pairing the second set of intermediate cars with an existing train.
“The formation of a six-car train and initial testing will require about two weeks. Following this, various software and hardware compatibility will be checked. Trial runs and safety tests will be conducted internally before starting commercial operations,” a senior official in BMRCL said.
Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.
Top News
Related Articles More
Drugs worth Rs 6 crore seized in Bengaluru, five arrested
Siddaramaiah urges Nirmala Sitharaman to address NABARD’s loan cuts to farmers
BJP stages protest against Congress govt in Karnataka over Waqf properties row
Loyalty Remembered: Mangaluru Airport’s K9 hero Jack passes away
Waqf issue: BJP stages Namma Bhoomi Namma Hakku protest in Bengaluru
MUST WATCH
Latest Additions
Air pollution: SC flags Delhi govt’s failure to implement GRAP-4 curbs on entry of trucks
Drugs worth Rs 6 crore seized in Bengaluru, five arrested
Siddaramaiah urges Nirmala Sitharaman to address NABARD’s loan cuts to farmers
Satwik-Chirag enter semifinals, Lakshya loses to Antonsen in China Masters
BJP stages protest against Congress govt in Karnataka over Waqf properties row
Thanks for visiting Udayavani
You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.