Temporary Gate Installation at Tungabhadra Dam: First Phase Successful
Team Udayavani, Aug 17, 2024, 8:56 AM IST
Koppal: The challenging task of installing a temporary replacement gate at the 19th crest gate of the Tungabhadra Reservoir, which had broken earlier, is progressing. On Friday night, one of the five stoplogs was successfully installed.
The technical team achieved their first milestone, boosting their confidence. The remaining four stoplogs are expected to be installed by Saturday evening.
On Friday morning, the crane removed the obstructing skywalk and the iron beams used for gate maintenance. By the evening, the experts prepared for the installation of the temporary gate.
Late at night, Minister Shivraj Thangadagi performed a special prayer before the installation began.
Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.
Top News
Related Articles More
Ullal: Auto-rickshaw accident near Konaje claims driver’s life
Congress victory in bypolls not a clean chit to CM in MUDA case: R Ashoka
Gangavati Railway Station to be renamed Anjanadri: M.B. Patil
Karkala: One-year-old leopard cub rescued from well in Nitte
JD(S) first family avoids discussion on Channapatna bypoll debacle
MUST WATCH
Latest Additions
No one has right to break law: BJP on Sambhal violence
Ullal: Auto-rickshaw accident near Konaje claims driver’s life
Congress victory in bypolls not a clean chit to CM in MUDA case: R Ashoka
IPL 2025 | Got someone who can do captaincy job: Ricky Ponting on Shreyas Iyer
Will review INDI alliance’s dismal performance in Maharashtra, says Tejashwi Yadav
Thanks for visiting Udayavani
You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.