Upper Bhadra Irrigation project expansion faces green hurdle
Team Udayavani, Jan 19, 2017, 3:47 PM IST
Bengaluru: Karnataka governments proposal to expand Upper Bhadra Lift Irrigation project to provide irrigation to Davanagere and Tumkur districts is facing green hurdle as a central panel has sought more details.
Recently, the Expert Appraisal Committee (EAC) under the Union Environment Ministry had examined the state governments proposal and deferred its decision on granting environment clearance (EC) for want of more information.
Originally, the project was designed to lift water from Tunga river to Bhadra reservoirs in two stages to irrigate the parched lands of Chikkamagalur and Chitradurga districts.
The stage-I of the project has got the EC and is underway. However in the stage-II, the state government has proposed expansion to extend irrigation facilities to farmers in Davanagere and Tumkur districts as well. Karnataka Neeravari Nigam Ltd (KNNL) is the implementing agency.
“After detailed deliberations, the EAC recommended that a sub-committee should visit the project site and submit a report on the viability of expansion of Upper Bhadra Lift Irrigation project,” a senior government official told PTI.
The central panel has noted that it would take a call on granting EC to the proposed expansion project after taking into account the inputs from the sub-committee, he said.
The EAC also observed that since lifting of water is sizeable, the economic viability of the lift irrigation project should be re-assessed based on the guidelines issued by Central Board of Irrigation and Power (CBIP), Delhi.
“The projects viability should be based on the actual cost of the energy at the consumers point (LIS). The cost of lifting per unit of water (cum) may also be worked out,” the EAC has noted.
Besides, the EAC said that the state government has proposed drip irrigation to be adopted for high-density crops like groundnut and its suitability should be re-ascertained.
The panel has also asked the state government to ensure that the land acquired for the project be suitably compensated with the prevailing guidelines and all commitments made during the Public Hearing should be fulfilled.
According to the proposal, the Upper Bhadra lift Irrigation Scheme envisages lifting of 17.40 TMC of water in Stage-I from Tunga river to existing Bhadra reservoir and lifting of 29.90 TMC of water in Stage-II from Bhadra reservoir to tunnel near Ajjampura in Tungabhadra sub-basin of Krishna basin.
After tunnel, through Chitradurga Branch Canal and Tumkur Branch Canal, it is planned to irrigate 2,25,515 ha area by drip irrigation in the districts of Chikkamagalur, Chitradurga, Tumkur and Davanagere.
Out of 29.90 TMC of water, 19.04 TMC of water is earmarked for irrigation and remaining 10.86 TMC is allocated for filling of 367 minor irrigation tanks. The entire water distribution will be automated and controlled by SCADA system. About 787 villages are likely to be benefitted under this project.
Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.
Top News
Related Articles More
Udupi: Bruhat Geetotsava concludes at Sri Krishna Matha
Priyank Kharge favours independent probe into Bidar contractor’s ‘suicide’, rejects BJP’s demand
Chikkamagaluru: Newlywed woman dies by suicide over severe abdominal pain
Beware of robbery on Bengaluru-Mysuru Highway: “Egg gang” raises its head
Bantwal: Teachers must make literature appealing to children, says Muliya Shankar Bhat
MUST WATCH
Latest Additions
Udupi: Bruhat Geetotsava concludes at Sri Krishna Matha
Space for Manmohan Singh’s memorial, Congress playing ‘cheap politics’: Nadda
Middleman held in connection with bribery case involving ED official: CBI
2 detained under PSA, PIT-NDPS Act in J&K’s Samba, Jammu
PM Modi calls Gukesh an embodiment of calmness and humility
Thanks for visiting Udayavani
You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.